References:
UMP glossary
Bibliography
Conventions & Notation
|
Activity 7.1.2: Management planning
| Task goals |
To define overall schedule, detailed iteration plan. |
| Procedure |
- Project Manager: Defines project structure.
- Project Manager: Estimates required resources.
- Project Manager: Defines development iterations.
- Project Manager: Get schedule approval.
- Developers: Prepare group (individual) plans
- Project Manager: Collects group (individual) plans and prepares detailed iteration plan.
- Project Manager: Agrees on detailed iteration plan with developers.
- Project Manager: Assigns tasks to developers.
- Project Manager: Publishes schedule and plan.
|
| Inputs |
Programming artifacts |
None |
| Model |
None |
| Documents |
|
| Checklists |
None |
| Guides |
Project management guide |
| Outputs |
Programming artifacts |
None |
| Model |
None |
| Documents |
|
| Checklists |
None |
| Completion criteria |
|
| Quality metrics |
|
| Milestones |
Before each iteration starts |
| Task improvement opportunity events |
|
|