Analysis tasks:

5.3.4.UMP1 Define Product Business Specifications
5.3.4.UMP2 Collect product requirements
5.3.4.1 Specify software requirements
5.3.4.UMP3 Develop UI prototype
5.3.8.4 Develop test cases
5.3.4.2 Evaluate SRS
5.3.4.UMP4 Evaluate UI prototype
5.3.8.5b Evaluate software test case

 

 

References:

UMP glossary
Bibliography
Conventions & Notation

 

Task 5.3.4.UMP2: Collect product requirements

UMP
  Development Process

         Software Requirements analysis Activity
<< previous task | next task >>

 

Task goals To collect and analyze product Change Requests
Procedure
  1. Product manager: Establishes Change requesting procedure.
  2. Product manager: Manages Change requests tracking.
  3. Product manager: Analyzes changes in cost, benefits and the overall impact on the current development plan.
  4. Product manager: Prioritizes the requested changes and proposes ensuing changes in the plan.
  5. Project Manager: Incorporates the accepted requests into the current plan for subsequent implementation.
  6. Project Manager: If necessary, agrees with the customers (sponsors, investors) on the changes in the development plan.
  7. Project Manager: Publishes the updated development plan.
Inputs Programming artifacts
  • Previous product iterations
  • Previous product version
  • Analogous product
  • Competitive product
Model None
Documents Change request
Checklists Change request evaluation checklist
Guides None
Outputs Programming artifacts None
Model None
Documents
Checklists None
Completion criteria  
Quality metrics  
Milestones  
Task improvement opportunity events
  • Change requests are not collected
  • Change requests are not prioritized
  • Change requests cannot be accessed by project participants
  • Change requests are not traced to PBS

 

 